Contract Signing18 February 2025
Site Mobilization and Land Grading25 February 2025
Mounting Structure Installation7 March 2025
Solar Panel Installation21 March 2025
Testing and Commissioning30 April 2025
Commissioned18 May 2025

This 20 MW commercial PV installation was executed to serve an industrial client aiming to reduce its carbon footprint and energy cost. Steelbridge Export led the entire EPC process including BOQ finalization, construction supervision, QA/QC enforcement, and grid synchronization. The project utilized HJT 700W panels, Sungrow SG250HX inverters, and a smart monitoring platform. The system is optimized for desert performance and includes sand-resistant mounting structures designed for 30-year durability.